MOUNT VERNON — Crews will close two downtown streets Monday, Nov. 23, to demolish three buildings north of the former City Hall.
The shutdown will begin at 8 a.m. for North Main Street between Public Square and Chestnut Street and East Chestnut Street between North Main and North Gay Street.
Interim City Engineer Quentin Platt said the streets will reopen for the Thanksgiving holiday weekend. The demolition contractor will remove fencing and reopen the roads at the end of the day Wednesday, Nov. 25.
“There will still be some parking restrictions on the east side of Main Street, as there currently are, but we do want to make sure that people are able to get around during the high-traffic shopping time of year and access the small businesses downtown,” he said.
Demolition and closures will resume Monday, Nov. 30. Platt hopes the contractor will complete the work that week. He expects the streets to reopen on Friday, Dec. 4.
Once the demolition is complete, on-street parking on the east side of North Main between Public Square and East Chestnut Street will reopen to the public.
The closures affect northbound State Route 13 and southbound State Route 3. The following are the posted detours.
• State Route 13 northbound: Motorists northbound on Gay Street should turn left (west) onto East High Street, follow Public Square to West High Street, then turn right (north) onto North Sandusky Street.
• State Route 3 northbound: Motorists on Public Square should turn right (east) onto East High Street, left (north) onto North Gay Street, and then turn right (northeast) onto Wooster Road.
• For State Route 3 southbound: Turn right (west) onto West Chestnut Street, left (south) onto North Norton Street, and then right (west) onto West High Street.
A contentious road to demolition
The city bought the buildings at 10-16 and 18-20 N. Main St., 6-8 E. Chestnut St., and 3 E. High St. in July 2022. Officials planned to demolish all four buildings to make way for a new justice center and city annex.
The condemned buildings have serious safety, mechanical and structural issues. When the city evicted a prior tenant, two employees of a subcontractor came into contact with methamphetamine and required hospitalization.
Residents opposed demolishing the North Main and East Chestnut buildings because they are historic buildings. One is the last remaining Henry B. Curtis building in the downtown area.
The Board of Property Maintenance Appeals condemned the buildings in March after a windstorm further damaged the buildings.
In August, the Historical Review Commission followed suit.
Once demolition is complete, the city plans to use the parcels for parking for the Mount Vernon Municipal Court staff. Current plans call for the court to move into 40 Public Square.
(Below is a PDF of the proposed preliminary design for the lot. )